Re-roofing usually needs Building Regulations approval when most or all of the roof is replaced, and in England and Wales a roofer registered with a competent person scheme can certify it for you, so you never deal with the council. What the rules add to a typical £9,000 new roof is mostly insulation: bringing the roof up to current standards while it is open. Small repairs and patching do not need approval.
When re-roofing needs Building Regulations approval
There is no single UK-wide threshold, and councils word their guidance differently, so treat these as the usual position rather than a rule:
- Re-covering a large part of the roof. Councils commonly draw the line at a quarter or a half of the roof area. Above it, the work is notifiable and the roof normally has to be insulated to current standards. Welsh Government guidance uses a quarter.
- Changing the covering. Going from slate to concrete tiles, or the other way, changes the weight on the roof structure, so it needs checking for strength even if the area is small.
- Structural work. Cutting rafters for a roof window, removing a chimney or altering the roof timbers needs approval whatever the area.
- Flat roofs. Replacing the waterproof covering, rather than patching it, counts as renovating the roof, and the insulation normally has to be upgraded.
Like-for-like repairs, such as replacing slipped tiles, rebedding a ridge or patching a flat roof, do not need approval.
What the Building Regulations add to a re-roofing job
The application itself is the small part. The real cost is the insulation that comes with it, set by Approved Document L in England. On a pitched roof over an ordinary loft that usually means topping up the loft insulation, which is cheap. On a room in the roof, or a flat roof over a kitchen or bedroom, it means insulation at rafter or deck level, which adds height at the edges and can add a substantial sum.
Changing the covering can add structural work. Heavy concrete tiles on rafters sized for slate may need the rafters strengthening, which an engineer checks against Approved Document A.
Who deals with it
In England and Wales there are three routes:
- A competent person scheme. A roofer registered with a government-authorised scheme, such as CompetentRoofer, notifies the council and certifies the work themselves. This is the simplest route and costs you nothing extra beyond the roofer’s own fee. The government lists the competent person schemes.
- The council’s Building Control. You or your roofer apply, pay the council’s fee, and an inspector visits.
- A registered building control approver. A private firm does the same job as the council.
Whichever route, you should receive a completion certificate at the end. Keep it: a buyer’s solicitor will ask for it, and a roof replaced without one can hold up a sale.
Scotland and Northern Ireland
Scotland has its own building standards, and the trigger is a building warrant rather than Building Regulations approval. Some work can go ahead without a warrant but must still meet the standards, as set out in the technical handbook. Ask your council’s building standards team before starting anything more than a repair.
Northern Ireland has its own Building Regulations, enforced by the building control departments of the eleven councils through Building Control Northern Ireland. The competent person schemes that cover England and Wales do not apply, so the council is usually the route.
Planning permission is separate
Building Regulations are about how the work is done. Planning permission is about how the house looks, and re-roofing in a similar material does not usually need it. Changing to a noticeably different covering can, and so can almost any change to a listed building or a house in a conservation area. A slate roof on a listed house, for instance, usually has to be renewed in slate.
Before the roof comes off
- Ask every roofer which route they will use, and whether they are registered with a competent person scheme.
- Ask what insulation is included, and to what standard, so the quotes compare like with like.
- Check whether the covering is changing, and if so, whether the timbers have been checked.
- Make sure the completion certificate, or the scheme’s certificate, is in the price and in your hands at the end.
Whether it is a typical new roof at about £9,000, a re-felt at about £4,800 or a flat roof replacement at about £2,800, the regulations are part of the job. Ask the roofer to price them in rather than leaving you to find out.